Abstract
Mechanical and electrical (M&E) services project is complex in nature and involves a large number of specialist organisations entering the project life cycle at different stages with different lines of relationships,
responsibilities and risk management capabilities. Hence, a number of risk arises at the design and installation stages which results into poor cost and time performance in M&E services projects. This paper identified and
rank the risk factors affecting cost and time performance of M&E services project. A total of 30 risk factors
identified from preliminary investigations was adopted as basis for a questionnaire survey to industry
practitioners in Nigeria. Mean response analysis was used to determinedthe probability and severity of the
risk factors and risk impact scores was used to rank the relative importance of the risk factors. Analysis of
variance (ANOVA) was used to investigate differences of opinions between respondents'. The study
identified 23 risk factors (risk impact >3.5) impacting M&E service projects. Out of these risk factors, 7 has
significant impact while the rest havemoderate impact. The 7 risk factors in order of their significance are: high
foreign materials content, poorly prepared tender documemt, late involvment of M&E engineers,noninvolvement
of specialist designers, government policy change, poor specification and poor coodination of
design imputs. In addition,ANOVAresults showthat no significant difference exists amongthe professionals
on these 7 risk factors.This suggests that the risk level of M&E services project is high.The identification and
ranking of the risk factors has practical implication inM&Eservices project. The risk identification and ranking
table is a good tool for assessment of risks related toM&Eservices at project inception. This will allow the client
and contractor to understand the high risk areas in M&E services project and, where applicable, assign
responsibility for those risks to theparty orparties best situated to control them.